Translate

Monday, December 30, 2013

FIELD TESTS ON CEMENT

Field tests on cements are carried to know the quality of cement supplied at site. It gives some idea about cement quality based on colour, touch and feel and other tests.
field-tests-on-cement

The following are the field tests on cement:

(a) The colour of the cement should be uniform. It should be grey colour with a light greenish shade.
(b) The cement should be free from any hard lumps. Such lumps are formed by the absorption of moisture from the atmosphere. Any bag of cement containing such lumps should be rejected.
(c) The cement should feel smooth when touched or rubbed in between fingers. If it is felt rough, it indicates adulteration with sand.
(d) If hand is inserted in a bag of cement or heap of cement, it should feel cool and not warm.
(e) If a small quantity of cement is thrown in a bucket of water, the particles should float for some time before it sink.
(f) A thick paste of cement with water is made on a piece of glass plate and it is kept under water for 24 hours. It should set and not crack.
(g) A block of cement 25 mm ×25 mm and 200 mm long is prepared and it is immersed for 7 days in water. It is then placed on supports 15cm apart and it is loaded with a weight of about 34 kg. The block should not show signs of failure.
(h) The briquettes of a lean mortar (1:6) are made. The size of briquette may be about 75 mm ×25 mm ×12 mm. They are immersed in water for a period of 3 days after drying. If cement is of sound quality such briquettes will not be broken easily.

PERMANENT FORMWORK METHOD FOR BEAM CONSTRUCTION

Permanent formwork construction method is used to:
  • Speed construction, especially of downstand beams
  • Provide high-quality finishes
  • Promote low tolerances
The units can act solely as permanent formwork, i.e. they may be designed for construction loads only without contributing to the strength of the completed beams.
More efficiently, they can act compositely with the in-situ concrete. Indeed some beams, particularly in seismic areas are designed to act both compositely and non-compositely in the same span.

Non-Composite Permanent Formwork:

Non-Composite Permanent Formwork
Non-composite precast permanent formwork is used to speed the erection process and assure quality finish. This is particularly useful on exposed spandrel beams which require specialized finishes or profiles. Polystyrene void formers can be introduced into rectangular sections to reduce self weight.
Non-Composite Permanent Formwork
Non-Composite Permanent Formwork
Non-Composite Permanent Formwork
The above units can be used in the main elevations supported by trestles and column formwork used in the curved elevation.

Composite Permanent Formwork:

Beam shells perform number of functions:
  • They are generally designed to support precast floor units and construction loads
  • To act as formwork for infill in-situ concrete
  • To act compositely with the in-situ infill to support permanent loads.
Their most common use is to form downstand beams. The units are usually in a U-form. The units may be reinforced or prestressed and once concreted, may be post-tensioned. Thin plain sections may incorporate lattice girders for temporary rigidity and to support construction loads.
Melbourne Cricket Ground, Southern Stand
Precast beam shells were chosen for speed of construction and quality of finish. The shells were made from grade 60 concrete and were placed at 7m centres to support hollowcore floor units.
Composite Permanent Formwork
Once supplementary reinforcement and tendons had been fixed, the shells and floor units were concreted with a grade 40 mix. The composite beams and floors were subsequently post-tensioned to obviate cracks. A four-day cycle was achieved.

FAILURE OF PILE FOUNDATION & REMEDIES

Pile foundation is widely used deep foundation for complex geologic conditions with kinds of load conditions, especially for soft soil foundation.  Pile foundation has large bearing capacity, well stability and  small differential settlement compared to other foundation types. But pile foundations may also get damaged and fail specially during earthquakes.
Pile foundation failure
Fig: Pile foundation failure
The failure of the pile foundation may result from any of the following causes:
  1. Lack of adequate boring
  2. Inaccurate soil classification
  3. Soft strata under tip of pile
  4. Inadequate driving formula (wrong data)
  5. Improper size of hammer cause insufficient penetration, too light or damaged if too heavy
  6. Misinterpretation of load
  7. Damaged of encased piles
  8. Buckling of piles
  9. Breaking of piles
  10. Vibration that cause lateral or vertical movement
  11. Flowing strata caused  by adjacent excavation or bank sloughing
  12. Tension failure of concrete pile for lack of reinforcement
  13. Eccentricity due to bowing or falling out of plumb
  14. Decay due to lower ground water level
  15. Insect and marine borer attack and corrosion
  16. Disintegration of concrete due to poor quality of concrete or reactive aggregate
  17. Collapse of the thin shell of the piles
  18. Overweight due to earthfill.
Remedies to prevent failure of pile foundation:
  1. Early repair such as encasement or replacement
  2. Removal of partial load
  3. Underpinning
Read More about Pile Foundations

THIN SHELL CONCRETE STRUCTURE–TYPES & FORMS

Special Forms for Concrete Shells

A thin shell concrete structure, is a structure composed of a relatively thin shell of concrete, usually with no interior columns or exterior buttresses. The shells are most commonly flat plates and domes, but may also take the form of ellipsoids or cylindrical sections, or some combination thereof.

Types and Forms of Shell Structure

  • Folded Plates
  • Barrel Vaults
  • Short Shells
  • Domes of Revolution
  • Folded Plate Domes
  • Intersection Shells
  • Warped Surfaces
  • Combinations
  • Shell Arches

Folded Plates

THIN SHELL CONCRETE STRUCTURE
The elements of a folded plate structure are similar to those of a barrel shell except that all elements are planar, and the moments in the slab elements are affected by the differential movement of the joints.
For the structure shown, the end supports and the side supports are both complete walls

THIN SHELL CONCRETE STRUCTURE

THIN SHELL CONCRETE STRUCTURE

Barrel Shells

THIN SHELL CONCRETE STRUCTURE
The elements of a barrel shell are:
(1) The cylinder,
(2) The frame or ties at the ends, including the columns, and
(3) The side elements, which may be a cylindrical element, a folded plate element, columns, or all combined.
For the shell shown in the sketch, the end frame is solid and the side element is a vertical beam.
A barrel shell carries load longitudinally as a beam and transversally as an arch. The arch, however, is supported by internal shears, and so may be calculated.
The elements of a folded plate structure are similar to those of a barrel shell except that all elements are planar, and the moments in the slab elements are affected by the differential movement of the joints.
For the structure shown, the end supports and the side supports are both complete walls
THIN SHELL CONCRETE STRUCTURE
The elements of a short shell are the barrel, which is relatively short compared to radius, the element at the base of the cylinder to pick up the arch loads, and the arches or rigid frame to pick up the entire ensemble. In this case it is a rigid frame arch. The size of the arch could have been reduced by horizontal ties at the springings. There may be multiple spans.
The short shell carries loads in two ways:
(1) As an arch carrying load to the lower elements. and
(2) As as a curved beam to the arches.
The thickness of the shell can be quite thin due to these properties.

Domes

THIN SHELL CONCRETE STRUCTURE
Domes are membrane structures, the internal stresses are tension and compression and are statically determinate if the proper edge conditions are fulfilled. In a dome of uniform thickness, under its own weight, the ring stresses are compression until the angle to the vertical is about 57 degrees. If the dome is less than a full hemisphere, a ring is required at the base of the dome to contain the forces.

Translation Shells

THIN SHELL CONCRETE STRUCTURE
A translation shell is a dome set on four arches. The shape is different from a spherical dome and is generated by a vertical circle moving on another circle. All vertical slices have the same radius. It is easier to form than a spherical dome.
The stresses in a translation shell are much like a dome at the top, but at the level of the arches, tension forces are offset by compression in the arch. However there are high tension forces in the corner.

Advantages of Concrete Shells

Like the arch, the curved shapes often used for concrete shells are naturally strong structures, allowing wide areas to be spanned without the use of internal supports, giving an open, unobstructed interior. The use of concrete as a building material reduces both materials cost and a construction cost, as concrete is relatively inexpensive and easily cast into compound curves. The resulting structure may be immensely strong and safe; modern monolithic dome houses, for example, have resisted hurricanes and fires, and are widely considered to be strong enough to withstand even F5 tornadoes.

Disadvantages of Concrete Shells

Since concrete is porous material, concrete domes often have issues with sealing. If not treated, rainwater can seep through the roof and leak into the interior of the building. On the other hand, the seamless construction of concrete domes prevents air from escaping, and can lead to buildup of condensation on the inside of the shell. Shingling or sealants are common solutions to the problem of exterior moisture, and dehumidifiers or ventilation can address condensation.

SAFETY MANAGEMENT AT CONSTRUCTION SITE

SAFETY MANAGEMENT IN CONSTRUCTION
  • Good house keeping should be maintained at all situations.
  • Safety hemlets, shoes, belts should be given to the workers to avoid the causes of injuries
  • Do not interfere with fire fighting equipment and electrical circuits
  • Proper labour shed has to be provided to the labour
  • Proper ventilation, lighting facilities, drinking water and sanitary facilities should be provided to the labour
  • Ensures Implementation of law of the land with respect to safety and health.
  • Create safety organization with Health and First aid facilities.
  • Adequate budget.
  • Standard, quality & timely supply of personnel protective equipment.
  • Neat based and adequate safety auditing and training to site management team & others
  • Organization for house keeping and deployment of qualified P& M person.
  • Incident and injury free work place.
  • Safety promotional activities.
  • Availability of recognized health care center.
  • Adequate provision of fire prevention systems.
  • No child labour.
  • No smoking.
  • Appropriate badges for identification of JMC staffs, contractors and others.
  • Formation of safety committee.
  • Workers will be covered under occupation accident policy.
  • Monitoring of implementation
safety
RESPONSIBILITIES OF SAFETY ENGINEER
  • Before commencing any work on site, Safety Officer is appointed who will ensure the safety measures at site
  • The safety measures to be adopted at the site will be the responsibilities of the Engineer executing the work
  • The safety officer will go for safety rounds all over the site every day and advise the concerned Supervisor regarding any unsafe act or condition and the remedial action required will be implemented.
  • Safety trainings will be conducted to all workers and staff before they start their work and as well as at regular intervals.
  • Those records of trainings will be maintained by safety officer.

Stem wall- slab foundation-cross section


Sunday, December 22, 2013

ADVANTAGES OF PRE-ENGINEERED BUILDING SYSTEMS

There are many advantages of pre-engineered building systems, but all advantages lead to reduced construction time. Following are advantages of Pre-Engineered Building Systems:

Reduced Construction Time:

Due to the systems approach, the use of high strength steel, use of tapered built-up sections which are optimized by the computerized design program and the use of continuous light gage secondary steel section, there is an overall reduction in steel weight, cost and time relative to conventional steel construction.
Pre-engineered buildings are a predetermined inventory of raw materials that has proven over time to satisfy a wide range of structural and aesthetic requirements. The components are engineered beforehand and standardized. Use of these standard components reduces the engineering, production and erection time. Use of customized software for design & drafting increases the speed of the project.
The production line is highly sophisticated, having Auto welders, multi-cutting torches, shear cutting machines etc., which greatly reduce the time of fabrication of built-up components. Roll forming machines for producing Z & C members and sheeting, having standard dimension, increases the production capacity of secondary members. Use of standard accessories greatly increases the speed of production & erection.
Buildings are typically delivered in just a few weeks after approval of drawings. Foundation and Anchor Bolts are cast in parallel with manufacture of the building. Site assembly is fast, as all building components are delivered finished, ready for site bolting.
It can reduce total construction time on a project by at least 50%. This will allow faster occupancy and earlier realization of revenue.
Pre-Engineered Building System

Design:

Since PEB’s are mainly formed of standard sections and connections, the design time is significantly reduced. Specialized computer analysis and design programs optimize material require. Drafting also computerized using standard details that minimizes project
custom details. The low-weight flexible frames offer higher resistance to seismic forces.

Lower Cost:

Due to the systems approach, there is a significant saving in design, manufacturing and site erection cost. The structural elements are shaped to follow the stress diagram of the member, thus reducing weight, cost and load to foundations. The secondary members
and cladding nest together reducing transportation cost. The overall price per square meter may be reduced as much as 30% lower than conventional steel.

Foundations:

Pre-engineered Buildings are about 30% lighter than the conventional steel structures. Hence, the foundations are of simple design, easy to construct and lighter weights.

Erection:

Since all the connections of the different components are standard, the erection time is faster.

Flexibility of Expansion:

Buildings can be easily expanded in length by adding additional bays. Also, expansion in width and height is possible by pre-designing for future expansion.

Large Clear Spans:

Buildings can be supplied to around 90M clear spans.

Quality Control:

As buildings are manufactured completely in the factory under controlled conditions, the quality is assured.

Low Maintenance:

Buildings are supplied with high quality paint systems for cladding and steel to suit ambient conditions at site, which results in long durability and low maintenance costs.

Energy Efficient Roof and Wall Systems:

Buildings can be supplied with polyurethane insulated panels or fibreglass blanket insulation to achieve required ‘U’ values.

Architectural Versatility:

Buildings can be supplied with various types of fascias, canopies, and curved eaves and designed to receive pre-cast concrete wall panels, curtain walls, block walls and other wall systems.

Single Source Responsibility:

As the complete building package is supplied by a single vendor compatibility of all the building components and accessories is assured. This is one of the major benefits of the pre-engineered building systems.

VACUUM CONCRETE: TECHNIQUES, EQUIPMENTS & ADVANTAGES

Water-cement ratio is detrimental for concrete. We always try to restrict the water-cement ratio in order to achieve higher strength. The chemical reaction of cement with water requires a water-cement ratio of less than 0.38, whereas the adopted water-cement ratio is much more than that mainly because of the requirement of workability. Workability is also important for concrete, so it can be placed in the formwork easily without honeycombing.
After the requirement of workability is over, this excess water will eventually evaporate leaving capillary pores in the concrete. These pores result into high permeability and less strength in the concrete. Therefore, workability and high strength don’t go together as their requirements are contradictory to each other.
Vacuum concrete is the effective technique used to overcome this contradiction of opposite requirements of workability and high strength. With this technique both these are possible at the same time.
In this technique, the excess water after placement and compaction of concrete is sucked out with the help of vacuum pumps. This technique is effectively used in industrial floors, parking lots and deck slabs of bridges etc. The magnitude of applied vacuum is usually about 0.08 MPa and the water content is reduced by upto 20-25%. The reduction is effective upto a depth of about 100 to 150 mm only.

Technique and Equipments for Vacuum Concrete:

The main aim of the technique is to extract extra water from concrete surface using vacuum dewatering. As a result of dewatering, there is a marked reduction in effective water-cement ratio and the performance of concrete improves drastically. The improvement is more on the surface where it is required the most.
Mainly, four components are required in vacuum dewatering of concrete, which are given below:
  1. Vacuum pump
  2. Water separator
  3. Filtering pad
  4. Screed board vibrator
Vacuum pump is a small but strong pump of 5 to 10 HP. Water is extracted by vacuum and stored in the water separator. The mats are placed over fine filter pads, which prevent the removal of cement with water. Proper control on the magnitude of the water removed is equal to the contraction in total volume of concrete. About 3% reduction in concrete layer depth takes place. Filtering pad consists of rigid backing sheet, expanded metal, wire gauge or muslin cloth sheet. A rubber seal is also fitted around the filtering pad as shown in fig.1. Filtering pad should have minimum dimension of 90cm x 60cm.
Vacuum dewatering of concrete
Fig. 1: Vacuum dewatering of concrete

Advantages of vacuum concreting:

  • Due to dewatering through vacuum, both workability and high strength are achieved simultaneously.
  • Reduction in water-cement ratio may increase the compressive strength by 10 to 50% and lowers the permeability.
  • It enhances the wear resistance of concrete surface.
  • The surface obtained after vacuum dewatering is plain and smooth due to reduced shrinkage.
  • The formwork can be removed early and surface can be put to use early.

Effect of vacuum dewatering of concrete
Fig. 2: Effect of vacuum dewatering of concrete
The advantages of dewatering are more prominent on the top layer as compared to bottom layer as shown in fig. 2 above. The effect beyond a depth of 150mm is negligible.

Tuesday, December 17, 2013

TYPICAL CONSTRUCTION JOINTS IN BEAMS AND COLUMNS

Construction joints are required when the concreting has to be stopped for the day or more than 30minutes. In such case, typical construction joints shall be provided so that bond is maintained between set concrete and fresh concrete. Below are some images showing correct method of construction joints to be provided in columns, beams and beam-column junction. To know about what is construction joint, read Joints in Concrete Construction.

1. Construction Joint in Column

Following figure shows correct method of providing construction joint in column. Construction joint in column shall not be provided with smooth surface or inclined surface. The top surface of the column should be rough with parts of coarse aggregates being seen.
construction-joints-in-column
Fig: Typical Construction Joint in RCC Column

2. Construction Joint in Beams and Beam-Column Joint:

Following figure shows the typical construction joint to be provided in beams and beam column joints.
Construction Joint in Beams and Beam-Column Joint
Fig: Typical Construction Joint in Beams and Beam-Column Joint
The arrow symbol shows the direction of concreting, tick mark shows the correct method of providing construction joint while cross-mark shows the wrong method.

JOINTS IN LIQUID RETAINING CONCRETE STRUCTURES

1. MOVEMENT JOINTS:

There are three types of movement joints.
(i) Contraction Joint: It is a movement joint with deliberate discontinuity without initial gap between the concrete on either side of the joint . The purpose of this joint is to accommodate contraction of the concrete. The joint is shown in Fig. 1 (a).
Contraction Joint in Water Tanks

Fig. 1(a)

A contraction joint may be either complete contraction joint or partial contraction joint. A complete contraction joint is one in which both steel and concrete are interrupted and a partial contraction joint is one in which only the concrete is interrupted, the reinforcing steel running through as shown in Fig. 1(b) .
Contraction Joint in Water Tanks`
Fig. 1
(ii) Expansion Joint: It is a joint with complete discontinuity in both reinforcing steel and concrete and it is to accommodate either expansion or contraction of the structure. A typical expansion joint is shown in Fig.2.
Expansion Joint in Water Tanks
Fig. 2.
This type of joint requires the provision of an initial gap between the adjoining parts of a structure which by closing or opening accommodates the expansion or contraction of the structure.
(iii) Sliding Joint: It is a joint with complete discontinuity in both reinforcement and concrete and with special provision to facilitate movement in plane of the joint . A typical joint is shown in Fig. 3.
Sliding Joint in Water Tanks
Fig. 3.
This type of joint is provided between wall and floor in some cylindrical tank designs.
2. CONTRACTION JOINTS
This type of joint is provided for convenience in construct ion. Arrangement is made to achieve subsequent continuity without relative movement. One application of these joints is between successive lifts in a reservoir wall. A typical joint is shown in Fig. 4.
Contraction Joint in Water Tanks
The number of joints should be as small as possible and these joints should be kept from possibility of percolation of water.

3. TEMPORARY JOINTS

A gap is sometimes left temporarily between the concrete of adjoining parts of a structure which after a suitable interval and before the structure is put to use, is filled with mortar or concrete completely as in Fig.5(a) or as shown in Fig.5 (b) and (c) with suitable jointing materials. In the first case width of the gap should be sufficient to al low the sides to be prepared before filling.
Temporary Joint in Water Tanks
Fig: 5 (a)
Temporary Joint in Water Tanks
Fig. 5(b)
Temporary Joint in Water Tanks
Fig. 5(c)

SPACING OF JOINTS IN LIQUID RETAINING CONCRETE STRUCTURES:

Unless alternative effective means are taken to avoid cracks by al lowing for the additional stresses that may be induced by temperature or shrinkage changes or by unequal settlement, movement joints should be provided at the following spacing:-
(a) In reinforced concrete floors, movement joints should be spaced at not more than 7.5m apart in two direct ions at right angles. The wall and floor joints should be in line except where sliding joints occur at the base of the wall in which correspondence is not so important .
(b)For floors with only nominal percentage of reinforcement (smaller than the minimum specified) the concrete floor should be cast in panels with sides not more than 4.5m.
(c) In concrete walls, the movement joints should normally be placed at a maximum spacing of 7.5m. In reinforced walls and 6m in unreinforced walls. The maximum length desirable between vertical movement joints will depend upon the tensile strength of the walls, and may be increased by sui table reinforcement . When a sliding layer is placed at the foundation of a wall , the length of the wall that can be kept free of cracks depends on the capacity of wall sect ion to resist the friction induced at the plane of sliding.
Approximately the wall has to stand the effect of a force at the place of sliding equal to weight of half the length of wall multiplied by the co-efficient of friction.
(d)Amongst the movement joints in floors and walls as mentioned above expansion joints should normally be provided at a spacing of not more than 30m between successive expansion joints or between the end of the structure and the next expansion joint ; al l other joints being of the construct ion type.
(e) When, however, the temperature changes to be accommodated are abnormal or occur more frequently than usual as in the case of storage of warm liquids or in uninsulated roof slabs, a smaller spacing than 30m should be adopted that is greater proportion of movement joints should be of the expansion type). When the range of temperature is small, for example, in certain covered structures, or where restraint is small , for example, in certain elevated structures none of the movement joints provided in small structures up to 45mlength need be of the expansion type. Where sliding joints are provided between the walls and either the floor or roof, the provision of movement joints in each element can be considered independently.

JOINTS IN CONCRETE CONSTRUCTION

Joints in concrete building construction are construction joints, expansion joints, contraction joints and isolation joints. They prevent cracking of concrete. Types of joints in concrete are described below:

Construction Joints:

Construction joints are placed in a concrete slab to define the extent of the individual placements, generally in conformity with a predetermined joint layout.
They must be designed in order to allow displacements between both sides of the slab but, at the same time, they have to transfer flexural stresses produced in the slab by external loads.
Construction joints must allow horizontal displacement right-angled to the joint surface that is normally caused by thermal and shrinkage movement. At the same time they must not allow vertical or rotational displacements. Figure 1 summarizes which displacement must be allowed or not allowed by a construction joint.
clip_image001

Expansion joint

The concrete is subjected to volume change due to many reasons. So we have to cater for this by way of joint to relieve the stress. Expansion is a function of length. The building longer than 45m are generally provided with one or more expansion joint. In india recommended c/c spacing is 30m. The joints are formed by providing a gap between the building parts.

Contraction Joints

A contraction joint is a sawed, formed, or tooled groove in a concrete slab that creates a weakened vertical plane. It regulates the location of the cracking caused by dimensional changes in the slab. Unregulated cracks can grow and result in an unacceptably rough surface as well as water infiltration into the base, subbase and subgrade, which can enable other types of pavement distress. Contraction joints are the most common type of joint in concrete pavements, thus the generic term “joint” generally refers to a contraction joint. Contraction joints are chiefly defined by their spacing and their method of load transfer. They are generally between 1/4 – 1/3 the depth of the slab and typically spaced every 3.1 – 15 m
Joints in concrete structures

Isolation Joints

Joints that isolate the slab from a wall, column or drainpipe

Isolation joints have one very simple purpose—they completely isolate the slab from something else. That something else can be a wall or a column or a drain pipe. Here are a few things to consider with isolation joints:
  • Walls and columns, which are on their own footings that are deeper than the slab subgrade, are not going to move the same way a slab does as it shrinks or expands from drying or temperature changes or as the subgrade compresses a little.
Joints in concrete structures
Even wooden columns should be isolated from the slab.
  • If slabs are connected to walls or columns or pipes, as they contract or settle there will be restraint, which usually cracks the slab—although it could also damage pipes (standpipes or floor drains).
  • Expansion joints are virtually never needed with interior slabs, because the concrete doesn’t expand that much—it never gets that hot.
  • Expansion joints in concrete pavement are also seldom needed, since the contraction joints open enough (from drying shrinkage) to account for temperature expansion. The exception might be where a pavement or parking lot are next to a bridge or building—then we simply use a slightly wider isolation joint (maybe ¾ inch instead of ½ inch).
  • Blowups, from expansion of concrete due to hot weather and sun, are more commonly caused by contraction joints that are not sealed and that then fill up with non-compressible materials (rocks, dirt). They can also be due to very long unjointed sections.
Joints in concrete structures
Very long unjointed sections can expand enough from the hot sun to cause blowups, but this is rare.
  • Isolation joints are formed by placing preformed joint material next to the column or wall or standpipe prior to pouring the slab. Isolation joint material is typically asphalt-impregnated fiberboard, although plastic, cork, rubber, and neoprene are also available.
  • Isolation joint material should go all the way through the slab, starting at the subbase, but should not extend above the top.
  • For a cleaner looking isolation joint, the top part of the preformed filler can be cut off and the space filled with elastomeric sealant. Some proprietary joints come with removable caps to form this sealant reservoir.
  • Joint materials range from inexpensive asphalt-impregnated fiberboard to cork to closed cell neoprene. Cork can expand and contract with the joint, does not extrude, and seals out water. Scott Whitelam with APS Cork says that the required performance is what determines the choice of joint materials. How much motion is expect, exposure to salts or chemicals, and the value of the structure would all come into play—and of course the cost.
Polyethylene foam isolation joint material comes in various colors. C2 Products
  • At columns, contraction joints should approach from all four directions ending at the isolation joint, which should have a circular or a diamond shaped configuration around the column. For an I-beam type steel column, a pinwheel configuration can work. Always place the slab concrete first and do not install the isolation joint material and fill around the column until the column is carrying its full dead

SEALING MATERIALS FOR JOINTS IN CONCRETE

There are three types of joints in concrete construction, viz. construction joint, expansion joint and contraction joints. Learn more about Joints in Concrete Structures.

Materials for joints in water retaining structures and water tight structures

(1) Materials for joints in water retaining structures and water tight structures for sewage and effluent treatment shall be resistant to aerobic and anaerobic microbiological attack and resistant to attack by petrol, diesel oil, dilute acids and alkalis.
(2) Materials for joints in water retaining structures for potable and fresh water shall comply with the requirements of BS 6920.

Joint filler

Joint filler shall be firm, compressible, single-thickness, non-rotting filler. Joint filler for joints in water retaining structures and watertight structures shall be non-absorbent.

Bitumen emulsion

Bitumen emulsion for joints in water retaining structures and watertight structures shall comply with BS 3416. Bitumen emulsion for surfaces against which potable or fresh water will be stored or conveyed shall comply with BS 3416, type II.
joints-in-concrete-structures


Fig: Joints in concrete structures

Joint sealant

(1) Joint sealant shall be a grade suited to the climatic conditions of Hong Kong and shall perform effectively over a temperature range of 0°C to 60°C. Joint sealant for exposed joints shall be grey.
(2) Joint sealant other than cold-applied bitumen rubber sealant shall be:
(a) A gun grade for horizontal joints 15 mm wide or less and for vertical and inclined joints,
(b) A pouring grade for horizontal joints wider than 15 mm.
(3) Polysulphide-based sealant shall be a cold-applied two-part sealant complying with BS 4254. Polysulphide-based sealant for expansion joints in water retaining structures and watertight structures shall have a transverse butt-joint movement range of at least 20%.
(4) Polyurethane-based sealant shall be a cold-applied two-part sealant complying with the performance requirements of BS 4254.
(5) Hot-applied bitumen rubber sealant shall comply with BS 2499, type N1.
(6) Cold-applied bitumen rubber sealant shall be of a proprietary type.
(7) Joint sealant for joints in water retaining structures and water tight structures shall be as stated in Table-1.
(8) Primers and caulking material for use with joint sealant shall be of a proprietary type recommended by the joint sealant manufacturer.
(9) Different types of joint sealant and primers that will be in contact shall be compatible.
Table-1: Joint sealant for water retaining structures and water tight structures
Structure for retaining / excluding
Type of joint
Type of joint sealant
Sewage
All joints
Polyurethane based
Other than sewage
Expansion joint
Polyurethane based or Polysulphide based
Horizontal joints other than expansion joints
Hot applied bitumen rubber, Polysulphide based or polyurethane based
Vertical and inclined joints other than expansion joints
Polysulphide based, polyurethane based or cold-applied bitumen rubber

Bond breaker tape

Bond breaker tape shall be of a proprietary type recommended by the joint sealant manufacturer and approved by the Engineer. The tape shall be a polyethylene film with adhesive applied on one side and shall be the full width of the groove.

Bearing strip for sliding joints

Bearing strip for sliding joints shall consist of two plastic strips of a proprietary type approved by the Engineer. The strips shall be resistant to all weather conditions and to chemicals to which the structure will be subjected without impairing the reaction, durability or function of the strips.
The strips shall be of a type that will not require maintenance after installation. The strips shall be capable of withstanding a vertical load of at least 300 kN/m2 and shall have a maximum coefficient of friction of 0.3 under a constant shearing force.

Waterstops or water stoppers

Waterstops, including intersections, reducers and junctions, shall be of a proprietary type approved by the Engineer. Waterstops shall be natural or synthetic rubber or extruded polyvinyl chloride and shall have the properties stated in Table-2.
Table-2: Properties of waterstops or waterstoppers
Property of water stops
Rubber waterstops
PVC waterstops
Density
1100 kg/m3 (+/-5%)
1300 kg/m3 (+/-5%)
Hardness
60 – 70 IRHD
70 – 90 IRHD
Tensile strength
>/= 20 N/mm2
>/= 13 N/mm2
Elongation at break point
>450%
>285%
Water absorption
<5% by mass after 48 hours immersion
<0.15% after 24 hours immersion
Softness number
-           
42 – 52
While principles of concrete joints remains same, references may also be made to ACI 224.3R-95 Joints in Concrete Construction and IS:3414 – 1968 – Indian Standard Code of Practice for Design and Installation of Joints in Buildings (Reaffirmed in 2010).
Read More:
1. Joints in Concrete Construction
2. Joints in Liquid Retaining Structures

Monday, December 16, 2013

STAGES OF FRACTURE (CRACKING) IN CONCRETE

The stages of cracking (fracture) in concrete:
There are three stages of cracking or fracture in concrete. When we describe the cracking mechanisms, it is important to differentiate between the mode of crack initiation and how this occurs at the microscopic level, and the subsequent paths of propagation and the eventual macroscopic crack pattern at the engineering level.
Although some discontinuities exist as a result of the compaction process of fresh concrete, the formation of small fissures or micro-cracks in concrete is due primarily to the strain and stress concentrations resulting from the incompatibility of the elastic moduli of the aggregate and paste components.
Following are the Stages of Concrete Cracking:
Stage I: Even before loading, intrinsic volume changes in concrete due to shrinkage or thermal movements can cause strain concentrations at the aggregate–paste interface. Within this stage localized cracks are initiated at the microscopic level at isolated points throughout the specimen where the tensile strain concentration is the largest. This shows that these cracks are stable and, at this load stage, do not propagate
Stage II: As the applied load is increased beyond Stage I, initially stable cracks begin to propagate. There will not be a clear distinction between Stages I and II since stable crack initiation is likely to overlap crack propagation and there will be gradual transition from one stage to another. This is shown in Fig.1. During Stage II the crack system multiplies and propagates but in a slow stable manner in the sense that, if loading is stopped and the stress level remains constant propagation ceases.
Cracking stages in Concrete
The extent of the stable crack propagation stage will depend markedly upon the applied state of stress, being very short for ‘brittle’ fractures under predominantly tensile stress states and longer for more ‘plastic’ fractures under predominantly compressive states of stress.
Stage III: This occurs when, under load, the crack system has developed to such a stage that it becomes unstable and the release of strain energy is sufficient to make the cracks self-propagate until complete disruption and failure occurs. Once Stage III is reached failure will occur whether or not the stress is increased. This stage  starts at about 70–90 per cent of ultimate stress and is reflected in an overall expansion of the structure as signified by a reversal in the volume change behaviour. As stated above, the load stage at which this occurs corresponds approximately to the long-term strength of concrete.

EXCAVATION HAZARDS- THEIR EFFECTS AND PREVENTION

Different types of hazards are associated with excavation of soil. These hazards should be identified and preventive measures should be taken to avoid any accident at construction sites. The following table highlights hazards associated with excavation of soil during construction, their types, effects and preventive measures.
TYPE OF EXCAVATION
TYPE OF HAZARD
EFFECT OF HAZARD
PREVENTIVE MEASURES
Pit excavation upto 3m
Falling into pit
Personal injury
Provide guard rails / barricade with warning signal
Provide atleast two entries / exits
Provide escape ladders
Earth collapse
Suffocation /breathlessness
Buried
Provide suitable size of shoring and strutting if required.
Keep soil heaps away from the edge equivalent to 1.5m or depth of pit whichever is more.
Don’t allow vehicles to operate too close to excavated areas. Maintain atleast 2m distance from the edge of cut.
Maintain sufficient angle of repose. Provide slope not less than 1:1 and suitable depth of excavation in all soils except hard rock.
Battering / benching the sides.
Contact with buried electric cable
Gas / Oil Pipelines
Electrocution
Explosion
Obtain permission from competent authorities prior to excavation if required.
Locate the position of buried utilities by referring to plant drawings.
Start digging manually to locate the exact position of buried utilities and thereafter use mechanical means.
Pit excavation beyond 3m
Same as above plus flooding due to excessive rain / underground water
Can cause drowning situation
Prevent ingress of water
Provide ring buoys
Identify and provide suitable size dewatering pump or well point system
Digging in the vicinity of existing building / structure
Building / structure may collapse
Loss of health and wealth
Obtain prior approval of excavation method from local authorities.
Use under-pinning method.
Construct retaining wall side by side.
Movement of vehicles / equipments close to the edge of cut.
May cause cave-in or slides.
Person may get buried.
Barricade the excavated area with proper lighting arrangements.
Maintain atleast 2m distance from edge of cut and use stop blocks to prevent over-run.
Strengthen shoring and strutting.
Narrow deep excavations for pipelines etc.
Same as above plus frequent cave-in or slides
May cause severe injuries or prove fatal.
Battering / benching of sides.
Provide escape ladders.
Flooding due to hydro-static testing
May arise drowning situation
Same as above.
Bail out accumulated water.
Maintain adequate ventilation.
Rock excavation by blasting
Improper handling of explosives
May prove fatal
Ensure proper storage, handling and carrying of explosives by trained personnel.
Comply with the applicable explosive acts and rules.
Uncontrolled explosion
May cause severe injuries or prove fatal.
Allow only authorized persons to perform blasting operations.
Smoking and open flames are to be strictly prohibited.
Scattering of stone pieces to atmosphere
Can hurt people
Use PPEs like goggles, face mask, helmets etc.
Entrapping of persons / animals
May cause severe injuries or prove fatal
Barricade the area with red flags and blow siren before blasting.
Misfire
May explode suddenly
Do not return to site for atleast 20min or unless announced safe by designated person.
Piling work
Failure of pile-driving equipment
Can hurt people
Inspect piling rigs and pulley blocks before the beginning of each shift/
Noise pollution
Can cause deafness and psychological imbalance.
Use personal protective equipments like ear plugs, muffs etc.
Extruding rods/casing
Can hurt people
Barricade the area and install sign boards
Provide first aid
Working in the vicinity of live-electricity
Can cause electrocution / asphyxiation
Keep sufficient distance from live electricity as per relevant standard codes.
Shut off the supply if possible.
Provide artificial / rescue breathing to the injured.
excavation-hazard